CR Minerals Pumice Processing Plant

CR Minerals Pumice Processing Plant
Espanola, New Mexico

Owner: San Juan Pueblo/Rankin Hobbs

Engineer: Dean Oliver International

Project Size: 30,000 Square Feet

Contract Amount: $500,000

Completion Date: April 2006

MSR was responsible for installing new equipment and refurbishing and installing several pieces of used equipment, comprised of interconnecting conveying, pneumatic transfer, instrumentation, air quality equipment and approximately 5, 000 LF of various size and alloy piping. Micro sizing to a 5 micron was included, as well as bins, hoppers and a packaging circuit capable of 5 TPH incorporating bagging, plasticizing and wrapping. Also installed was a bulk bag circuit with 8 stations @ 17 TPH.